Test the agreed operating behaviour, not only whether the feeder runs.
A factory acceptance test (FAT) and site acceptance test (SAT) are most useful when the project has a clear specification, representative closures and agreed pass criteria. The FAT can demonstrate the feeder route in a controlled environment. The SAT then confirms installation, utilities, line signals, guarding, operator access and real handover to the capping machine.
The scope should be proportionate to the project. A stand-alone presenter may need a simpler test than a fully integrated hopper, elevator, orientator, chute and capper. In every case, the acceptance record should identify the exact cap and bottle formats tested, the test conditions, any exclusions and the actions required before handover.